Major Hazard Source Security Evaluation Report of Zhongneng International Petrochemical Co., Ltd

Time:2022-09-21
|
From:
|
Views:405
|
Font Size:Default Big Large
|
Print
|
1. Safety evaluation project name: Zhongneng International Petrochemical Co., Ltd. major hazard security evaluation report
2. Introduction to the safety assessment project:
 Zhongneng International Petrochemical Co., Ltd., formerly known as Huanghua Xinyi Chemical Co., Ltd., is a joint-stock company invested and established by Shandong Xinhe Chemical Group Company. It was established in December 2006 and the economic system category is a limited liability company. On October 26, 2015, the company was renamed Zhongneng International Petrochemical Co., Ltd., the legal representative is Wang Chao, and the registered capital is 680 million yuan. The company currently has 600,000 tons/year heavy oil catalytic cracking unit (discontinued), 600,000 tons/year redelivery asphalt unit (discontinued), 1 million tons/year delayed coking unit (500,000 tons/year for the first phase of the project), 300,000 tons/year hydrorefining unit and supporting projects. The company's 1 million tons/year delayed coking plant (500,000 tons/year for the first phase of the project), 300,000 tons/year hydrogenation refining device and supporting projects first obtained the safety production license in 2009. Since then, a qualified safety evaluation company has been entrusted every 3 years to conduct a safety status evaluation. After the evaluation, the safety production license was extended in 2019. Certificate number: (Ji) WH safety license word [2019] 090142. valid period: August 9, 2019 to August 8, 2022.
 According to the relevant regulations of the state and Hebei Province and the evaluation contract signed by Hebei Huafei Technology Consulting Co., Ltd. and Zhongneng International Petrochemical Co., Ltd., the evaluation scope is the external safety conditions of Zhongneng International Petrochemical Co., Ltd., the general layout and construction (structure) buildings, process systems and equipment facilities, public works and auxiliary works, safety management of major hazard sources, etc.
3. Safety evaluation project leader, technical person in charge, process control person in charge, evaluation report compiler, report auditor, safety evaluator involved in security evaluation work, registered safety engineer, technical expert:
  Safety evaluation project leader: Sun Guang
  Report Compilers: Sun Guang Gao Weili, Yang Jiangming, Zhang Peng, Ma Junxing
  Report Reviewer: Zhou Junhong
  Safety evaluators, registered safety engineers, and technical experts participating in the evaluation work: Sun Guang Gao Weili, Yang Jiangming, Zhang Peng, Ma Junxing
4. List of personnel, time, and main tasks to carry out safety evaluation work on site, and evaluation report time:
 In August 2021, Huafei Company established an engineering evaluation team and officially launched the evaluation work. The evaluators communicated with the relevant personnel of Zhongneng International Petrochemical Co., Ltd. for many times to collect relevant information. They went to the site to follow up the investigation and grasp the first-hand information data at the first time. During the evaluation process, the members of the evaluation team carefully analyzed and sorted out the relevant materials provided by the enterprise and collected on site. After solid and meticulous work, the major hazard source security evaluation report of this project was compiled and completed in December 2021.

Scan