Safety Assessment Report of Dangerous Chemicals in Dongfang Petroleum Products Supply Station in Gaoyang County

Time:2019-03-27
|
From:
|
Views:230
|
Font Size:Default Big Large
|
Print
|
1. Safety evaluation project name: Gaoyang County Dongfang Petroleum Products Supply Station Operating Hazardous Chemicals Safety Evaluation Report
2. Introduction to the safety assessment project:
Gaoyang County Dongfang Petroleum Products Supply Station is located in the south of Li Guozhuang Village, Gaoyang County. It was established in 1993 and is a collective business unit (unincorporated). The person in charge is Han Song and there are currently 6 employees. It mainly deals in two varieties of gasoline and diesel for vehicles. There are 6 directly buried horizontal SF storage tanks in the storage tank area, including 3 gasoline storage tanks of 20m3 and 3 diesel storage tanks of 20m3. There are 6 refueling machines in the refueling area, with double rows. The gasoline facilities are all equipped with oil and gas recovery systems. Covering an area of 212m2, the main buildings include station buildings, single-story buildings (including finance rooms, business halls, power distribution rooms, station master rooms, etc.), sheds, auxiliary rooms, tank pools, station building construction area of 175.5m2, auxiliary room area of 70m2, tank area of 230m2, canopy area of 680.4m2.
According to the relevant regulations of the state and Hebei Province, as well as the evaluation contract signed between Hebei Huafei Technology Consulting Co., Ltd. and Gaoyang County Oriental Petroleum Products Supply Station, the evaluation scope is the external safety conditions of the gas station of Gaoyang County Oriental Petroleum Products Supply Station, the general plane layout and construction (structure) buildings, process systems and equipment facilities (station buildings, tank areas, refueling areas and auxiliary facilities), public works and auxiliary works, safety management, etc.
3. Safety evaluation project leader, technical leader, process control leader, evaluation report compiler, report auditor, safety evaluator, registered safety engineer, and technical expert involved in the evaluation:
    Safety evaluation project leader: Wang Tongen
    Technical person in charge: Zhou Junhong
    Person in charge of process control: Wang Lin
    Compilers of the evaluation report: Wang Tongen, Sun Guang, Ma Junxing
    Report Reviewer: Gao Weili
    Safety evaluators, registered safety engineers, and technical experts participating in the evaluation work: Gao Weili, Sun Guang, Zhou Junhong, Wang Tongen, Ma Junxing, Wang Lin
4. List of personnel, time, and main tasks to carry out safety evaluation work on site, and evaluation report time:
  In September 2018, Huafei Company established an engineering evaluation team to officially start the evaluation work. The evaluators communicated with the stationmaster of Dongfang Petroleum Products Supply Station in Gaoyang County many times to collect relevant information. They went to the site to follow up the investigation many times and grasp the first-hand information and data at the first time. During the evaluation process, the members of the evaluation team carefully analyzed and sorted out the relevant materials provided by the enterprise and collected on site. After solid and meticulous work, the safety evaluation report of this project was compiled in early November 2018.